①技术优势 Technical Advantage
美森艺术零碳面材以及全钢结构的天、墙一体化的装配式装饰系统;
Meson Art zero-carbon surface material and the fabricated decoration system integrating ceilings, walls with all-steel structure;
实现装饰系统的标准化设计,部品部件工厂化生产,现场装配式安装;
Realize the standardized design of the decoration system, factory production of components and parts, and on-site fabricated installation;
所有部品部件可以无损拆卸,重复使用,二次改造及装修成本低;
All components and parts can be disassembled without damage, reused, and the cost of secondary renovation and decoration is low;
环保指标远高于国家标准,,零甲醛,竣工后即可
All environmental protection indicators are far higher than the national standards, with zero formaldehyde,and it is ready for occupancy immediately after completion;
实现管线分离,简化管线施工,解决管线维修难的问题;
Realize the separation of pipelines, simplify pipeline construction, and solve the problem of difficult pipeline maintenance;
灯具风口一体化,统一安装方式,减少专业之间的
The ceiling is integrated with the lamps and air vents, with a unified installation method, reducing conflicts among specialties;
墙体与柜体一体化,可节省使用空间,比传统工期节约 30% 以上;
The integrationof thewall and thecabinetcansave theuse space and savemore than 30% ofthetraditional constructionperiod;
采用美森零碳材料,钢型材龙骨、镀锌钢板等为基材,防火性能为A级;
Using Meson zero-carbon materials, steel profile keels, galvanized steel plates, etc. as base materials, the fire resistance performance is Grade A;
采用钢板为基材,可解决挂画及小空间收纳,或局部吊柜、隔板功能,无需增加墙体结构,及破坏饰面板。
Using steel plates as the base material can solve the problems of hanging pictures and storage in small spaces, or the functions of local wall cabinets and partitions. There is no need to add wall structures or damage the decorative panels.
{0}② 幕墙工程设计总则
General Design Principles of Curtain Wall Engineering
1.本说明为美森艺术零碳面材复合板幕墙工程指导说明,包括板材的设计、制作、安装施工以及验收。
This instruction is a guide for the Meson Art zero carbon composite panel curtain wall project, including the design, production, installation,construction, and acceptanceofthepanels.
2.美森艺术零碳面材复合板适用于建筑高度不大于100m、抗震设防烈度不大于8的民用建筑;各类商业、办公等场所的隔墙系统、吊顶系统、单墙系统。
Meson Art Zero Carbon Composite Panel is suitable for civil buildings with a height not exceeding 1oom and a seismic fortification intensity not exceeding 8; Partition systems, ceiling systems and single wall systems for various commercial and office spaces.
3.美森艺术零碳面材复合板幕墙系统的设计、制作以及安装施工实行全过程质量监控,除了需符合本规范之外,尚应当符合国家现行有关强制性标准的规定。
The design,production,and installation of the Meson Art zero carbon composite panelcurtainwallsystemshallbesubjecttofullprocessqualitymonitoring.In addition to complying with this specification,it shall also comply with the relevant mandatory standards of the country.
1.建筑幕墙 building curtain wall
由金属构架与板材组成的、不承担主体结构荷载与作用的建筑外围护结构。
A building envelope structure composed of metal frame and sheet metal, which does not bear the load and action of the main structure.
2.零碳面材 econiclay
以改性无机粉为主要原料,添加高分子聚合物,经成型、交联、加热、复合制成的,能表现各种砖、木材、石材、皮革、陶瓷、编织物和浮雕等效果的,厚度为2-10mm,具有柔性的可回收再生的轻质饰面片材。
A flexible, recyclable and lightweight facing sheet with a thickness of 2-10mm, which is made by adding high-molecular polymers to modified inorganic powder as the main raw material, and processed through forming, cross-linking, heating and compounding. It can show various effects such as bricks, wood, stone, leather, ceramics, woven fabrics and reliefs.
3.零碳面材复合板 econiclay coverings composite panel
采用零碳面材粘接铝蜂窝板、金属折边单板(如铝单板)或金属面岩棉夹芯板等形成的复合板材。
Composite panels formed by bonding zero-carbon surfacing materials with aluminum honeycomb panels, metal folded single panels (such as aluminum single panels), or metal surface rock wool sandwich panels, etc.
4.建筑幕墙 building curtain wall
板材为零碳面材复合板的建筑幕墙,板材的基本构造如图所示。
The building curtain wall with the panel being the zero-carbon surfacing material composite panel. The basic structure of the panel is shown as in the figure.
5.组合幕墙composite curtain wall
板材为零碳面材复合板等不同板材组成的建筑幕墙。
The building curtain wall composed of different panels such as zero-carbon surfacing material composite panels.
6.斜建筑幕墙 inclined building curtain wall
与水平面成大于 75°. 小于 *90°. 角的建筑幕墙。
Building curtain walls that form an angle greater than 75° and less than 90° with the horizontal plane.
7.单元建筑幕墙 unit building curtain wall
由金属构架、各种板材组装成一层楼高单元板块的建筑幕墙。 The building curtain wall composed of metal frameworks and various panels assembled into one-story high unit modules.
8. 小单元建筑幕墙 small unit building curtain wall
由金属副框、各种单块板材,采用金属挂钩与立柱、横梁连接的可拆装的建筑幕墙。 The detachable building curtain wall which is connected by metal sub-frames, various single panels, and metal hooks to the columns and beams.
04 美森装配式装饰系统解析
Analysis of Meisen Prefabricated Decoration System
1.幕墙系统结构说明
Description of the Structure of the Curtain Wall System
2.吊顶系统结构说明
Description of the Structure of the Ceiling System 吊顶可做多种造型、可嵌灯光,可根据具体要求进行设计。 The ceiling can have various shapes, can be embedded with lights, and canbe designed according to specific requirements.
\circled{1} M8膨胀螺栓 M8Expansion Bolt
\circled{2} M8螺纹吊杆 M8 Threaded Suspension Rod
\circled{3} M8螺母 M8 Nut
\circled{4} C50主龙骨吊扣 C50 Main KeelHanging Buckle
\circled{5} M6\*30对穿螺栓 M6\*30Through Bolts
\circled{6} 1.2mm厚C50主龙骨 1.2mm Thick C50 Main Keel
⑦ M4镀锌钢自钻自攻螺arling an slf-tapping Screws
\circled{8} 主副龙骨连接件 Connector for Main and Secondary Keels
⊚ 1.2mm厚配套Z型龙骨 1.2mm Thick Matching Z-shaped Keel
{10} 0.7mm厚镀锌钢吊顶面板 0.7mm Thick Galvanized Steel Ceiling Panel
{17} 2\*8mm密封胶条 2\*8mmSealStrip
3.单面挂墙系统结构说明
Description of the Structure of the Single-sided Wall-mounted System
4.组合隔墙系统结构说明
Structural Description of the Combined Partition Wall System
5.美森零碳面材种类介绍
IntroductiontothetypesofMesonZeroCarbonSurfaceMaterials
_01纯色系列Solid Color Series
灵秀洞石-1292
Stylish Travertine-1292
细布纹石-1283
Cloth patterned stone-Fine-1283
幽谷洞石-素白 Yougu Travertine-White
斧开石-1375
Axe-cut stone-1375
皓月石-素白 Bright Moonstone-White
冰珍石-1283
Ice-jade Stone-1283
斧琢-1285
Chisel Stone-1285
砂岩-素白 Sandstone-white
纹澜石-1264
Ripple Stone-1264
夯土板-0152
Rammed Earth Slab-0152
波浪板-1291
Corrugated Slab-1291
浇筑版-N675
Full Cast-N675
唐韵-0248
Tang Weaving-0248
023D艺术系列
3D Art Series
灵秀洞石-丝韵莲白 Stylish Travertine-Silk Rhyme Lotus white
灵秀洞石-天际浅灰 Stylish Travertine-Skyline Light grey
幽谷洞石-流光米白 Yougu Travertine-Flowing light Off-white
毛面石-迷踪墨黑Rough Stone-Lost Track Black
毛面石-潘多拉粉Rough Stone-Pandora Pink
大理石-清水暖灰Marble-lce Clear Water Warm Gray
抛光大理石-迷踪黑 Marble-Lost Track Black
天山岩-青岩Tianhan Rock-Green Rock
砂岩-星石天青 Sandstone-Star stone Cyan
砂岩-运纱粉韵 Sandstone-Cloudy Gauze Pink
冰珍石-清水雅黄 Ice-Jade Stone-Polish Concrete
冰珍石-清水墨染 Ice-Jade Stone-Polish Concrete Darkness
船木-胡桃Ship Timber-Peach colored
05 安装施工
Installation and Construction
1.一般规定GeneralProvisions
安装美森零碳面材复合板幕墙应在主体工程验收后进行。 The installation of theMeisenzero-carbon surface material compositepanel curtain wall should be carried out after the acceptance of the main project.
The material varieties, specifications, colors and performances of the components and accessories ofthecurtain wall shall comply with the design requirements.
,幕墙的安装施工应编制施工组织设计,其中应包括以下内容:
The installation andconstruction of the curtainwall shallpreparea constructionorganizationdesign,whichshallinclude the following contents:
_01工程进度计划; Project schedule plan;
02 搬运、起重方法; Handling and lifting methods;
_03测量方法; Measuring methods;
04 安装方法; Installation methods;
05 安装顺序; Installation sequence;
06检查验收; Inspection and acceptance;
_07安全措施。 Safety measures.
2.安装施工准备
Installation Construction Preparation
搬运、吊装构件时不得碰撞、损坏和污染构件。
When handling and hoisting components, they shall not be collided with, damaged orcontaminated. 构件储存时应依照安装顺序排列放置,放置架应有足够的承载力和刚度。
在室外储存时应采取保护措施。 When storing components, they should be placed in the installation sequence.
The storage racks should have sufficient bearing capacity and rigidity.
Protective measures should betakenwhen storing outdoors.
)构件安装前应检查制造合格证,不合格的构件不得安装。
Beforeinstalling the components,the manufacturing certificates should be checked. Unqualified components shall not be installed.
幕墙与主体结构连接的预埋件,应在主体结构施工时按设计要求埋设。预埋件应牢固,位置准确,预埋件的位置误差应按设计要求进行复查。当设计无明确要求时,预埋件的标高偏差不应大于10mm,预埋件位置差不应大于20mm。
Theembeddedpartsconnectingthecurtainwall and themainstructureshould beembeddedasrequiredbythedesignduring theconstructionofthemain structure.The embedded parts should be firm and in accurate positions.The positionerrorsoftheembeddedpartsshouldberecheckedasrequiredbythe design.whentherearenoclearrequirementsinthedesign,theelevation deviationof theembedded parts should notbegreaterthan10mm,and the positiondeviationof theembeddedpartsshould notbegreaterthan 20mm
3.幕墙安装施工
Curtain Wall Installation Construction 安装施工测量应与主体结构的测量配合,其误差应及时调整。 The measurement of installation construction should cooperate with the measurement of the main structure, and its errors should be adjusted in time.
幕墙立柱的安装应符合下列规定:
The installation of the curtain wall columns shall comply with the following provisions:
一01立柱安装标高偏差不应大于3mm,轴线前后偏差不应大于2mm,左右偏差不应大于3mm;
The elevation deviation of the column installation shall notbe greater than 3mm,thefront and rear deviation of the axis shall not be greater than 2mm and the left and right deviation shall not be greater than3mm;
02相邻两根立柱安装标高偏差不应大于3mm,同层立柱的最大标高偏差 不应大于5mm,相邻两根立柱的距离偏差不应大于 2mm Theinstallation elevation deviation of two adjacent columnsshall not be greaterthan3mm,the maximumelevation deviationof the columns on the same floorshall not be greater than 5mm, and the distance deviation between twoadjacent columns shall not begreater than 2mm.
幕墙横梁安装应符合下列规定:
The installation of the curtain wall beams shall comply with the following
regulations:
一01应将横梁两端的连接件及垫片安装在立柱的预定位置,并应安装牢 固,其接缝应严密; The connectingpieces and gaskets at both ends of the beam should be installed at thepredetermined positions of the column and should be firmly installed, and the joints should be tight;
02相邻两根立柱安装标高偏差不应大于3mm,同层立柱的最大标高偏差 不应大于5mm,相邻两根立柱的距离偏差不应大于 2mm The installation elevation deviation of two adjacent columns shall not be greater than3mm,the maximumelevation deviation of thecolumnson the same floor shallnot be greater than 5mm,and the distance deviation betweentwo adjacentcolumns shall not begreaterthan 2mm.
零碳面材复合板幕墙安装应符合下列规定:
The installation of the zero-carbon surfacematerial compositepanel curtain
wall shall complywiththefollowingregulations:
01应对横竖连接件进行检查、测量、调整; The vertical and horizontal connecting pieces should be inspected, measured and adjusted;
02幕墙安装时,左右、上下的偏差不应大于 1.5\mathsf{mm} When installing the curtain wall,the deviation to the left and right, and up anddownshallnotbegreaterthan 1.5mm
03板材空缝安装时,必须有防水措施,并应有符合设计要求的排水出口; When the plates are installed with empty joints, waterproof measures must be taken, and there should be drainage outlets that meet the design requirements;
04填充硅酮耐候密封胶时,板缝的宽度、厚度应根据硅酮耐候密封胶的 技术参数,经计算后确定。 Whenfillingthe siliconeweather-resistantsealant,thewidthand thickness of thepanel joints shouldbe determinedaftercalculation accordingtothetechnicalparametersofthesiliconeweather-resistant sealant.
幕墙钢构件施焊后,其表面应采取有效的防腐措施。
After theweldingofthesteelcomponentsof thecurtainwall,effective anti-corrosionmeasuresshould betakenontheirsurfaces.
幕墙的竖向和横向板材的组装允许偏差应符合表1的规定。
Theallowabledeviationsfortheassembly of thevertical and horizontal plates of the curtain wall shall comply with the regulations inTable 1.
| 项 目 | 尺寸范围 | 允许偏差 | 检查方法 |
| 相邻两竖向板材间距尺寸(固定端头) | ±2.0 | 钢卷尺 | |
| 两块相邻的板 | ±1.5 | 靠尺 | |
| 相邻两横向板材的间距尺寸 | 间距小于或等于2000时 | ±1.5 | 钢卷尺 |
| 间距大于2000时 | ±2.0 | ||
| 分格对角线差 | 对角线长小于或等于 2000时 | 0 | 钢卷尺或伸缩尺 |
| 对角线长大于2000时 | ≤3.5 | ||
| 相邻两横向板材的水平标高 | ≤2 | 钢板尺或水平仪 | |
| 横向板材水平度 | 构件长小于或等于2000时 | ≤2 | 水平仪或水平尺 |
| 构件长大于2000时 | |||
| 竖向板材直线度 | 2.5 | 2.0m靠尺、钢板尺 | |
| 板下连接托板水平夹角允许向上倾斜 /不准向下倾斜 | +2.0度/0 | 塞 规 | |
| 板上连接托板水平夹角允/许向下倾斜 | 0/-2.0度 |
幕墙安装允许偏差应符合下表2规定。
The allowable deviations for the installation of the curtain wall shall comply withtheregulationsinTable2.
| 项 目 | 允许偏差(mm) | 检查方法 | |
| 竖缝及 墙面垂 直 度 | 幕墙高度(H)(m) | ≤10 | 激光经纬 仪或经 纬仪 |
| H≤30 | |||
| 60≤H>30 | ≤15 | ||
| 90≤H>60 | ≤20 | ||
06| ≤25 | | ||
| 幕墙平面度 | ≤2.5 | 2m靠尺、钢板尺 | |
| 竖缝直线度 | ≤2.5 | 2m靠尺、钢板尺 | |
| 横缝直线度 | ≤2.5 | 2m靠尺、钢板尺 | |
| 缝宽度(与设计值比较) | ±2 | 卡尺 | |
| 两相邻面板之间接缝高低差 | ≤1.0 | 深度尺 | |
单元幕墙安装允许偏差除应符合本规范表2的规定外,尚应符合表3规定。
The allowabledeviationsfortheinstallationofunitcurtainwallsshall not only complywiththeregulationsinTable2of thiscodebutalsocomplywiththe requlationsinTable3.
| 项 | 目 | 允许偏差 | 检查方法 |
| 同层单元组件标高 | 宽度小于或等于35m | 0 | 激光经纬仪或经纬仪 |
| 相邻两组件面板表面高低差 | ≤1. 0 | 深度尺 | |
| 两组件对插件接缝搭接长度(与设计值比) | ±1. 0 | 卡尺 | |
| 两组件对插件距槽底距离(与设计值比) | ±1. 0 | 卡尺 | |
幕墙安装过程中宜进行接缝部位的雨水渗漏检验。
During the installation process of the curtain wall, it is advisable to conduct tests forrainwaterleakage at thejoint parts.
幕墙安装施工应对下列项目进行验收:
The following items shall be inspected and accepted during the installation construction ofthecurtainwall:
一01主体结构与立柱、立柱与横梁连接节点安装及防腐处理; The installation and anti-corrosion treatmentof the connection nodes between the main structure and the columns,and between the columns andthebeams;
02幕墙的防火、保温安装; The installation of fire protection and insulation of the curtain wall;
_03幕墙的伸缩缝、沉降缝、防震缝及阴阳角的安装; The installation of expansion joints, settlement joints, seismic joints and internaland external corners of the curtainwall;
04幕墙的防雷节点的安装; The installation of lightning protection nodes of the curtain wall;
05幕墙的封口安装。 The installation of the curtain wall's closures.
4.幕墙保护和清洗
Curtain wall protection and cleaning
对幕墙的构件、面板等应采取保护措施,不得发生变形、变色、污染等现象。 Protective measures should betakenfor the components andpanels of the curtain wall, and phenomena such as deformation, discoloration and pollution shouldnotoccur.
幕墙施工中其表面的粘附物应及时清除。
During the construction of the curtain wall, the adhered substances on its surface should beremoved intime.
幕墙工程安装完成后,应制定清洁方案,清扫时应避免损伤表面。
After the installation of the curtain wall project is completed, a cleaning plan shouldbeformulated.whencleaning,surfacedamage should be avoided. 清洗幕墙时,清洁剂应符合要求,不得产生腐蚀和污染。
When cleaning the curtain wall, the cleaning agent should meet the requirements and must not cause corrosion or pollution.
4.幕墙安装施工安全
Safety in theInstallation Construction of CurtainWall幕墙安装施工的安全措施除应符合现行行业标准《建筑施工高处作业安全技术规范》(GJ80)的规定外,还应遵守施工组织设计确定的各项要求。
Thesafety measuresfortheinstallationconstruction of curtain wallsshall not only comply with theprovisions of the current industry standard"Technical Specification for Safety of Working at Heights in Building Construction" (IGj80), but alsoabidebythe various requirements determinedinthe construction organizationdesign.
安装幕墙用的施工机具和吊篮在使用前应进行严格检查,符合规定后方可使用。
Theconstructionmachinesandgondolasusedfor installingthecurtainwall should be strictly inspected before use, and can be used only after meeting the requirements.
)施工人员作业时必须戴安全帽,系安全带,并配备工具袋。
When construction workers are working,they must wear safety helmets,fasten safety belts and be equipped with tool bags.
工程的上下部交叉作业时,结构施工层下方应采取可靠的安全防护措施。
When there are cross-operations in the upper and lower parts of the project, reliable safety protection measures should be taken below the structural constructionlayer.
现场焊接时,在焊接下方应设防火斗。
When welding on site,a fire prevention bucket should be set below the welding area.
脚手板上的废弃杂物应及时清理,不得在窗台、栏杆上放置施工工具。
The waste and sundries on the scaffold boards should be cleared in time, and construction toolsshould not beplaced on the window sills and railings.
工程验收
Project Acceptance
)幕墙工程验收前应将其表面擦拭干净。 The surface of the curtain wall project should be wiped clean before acceptance. 幕墙工程验收时应提交下列资料: The following materials should be submitted when the curtain wall project is accepted: 一01设计图纸、计算书、文件、设计更改的文件等; Design drawings, calculation books, documents, documents of design changes, etc.; 02材料、零部件、构件出厂质量合格证书,硅酮结构胶相容性试验报告 及幕墙的物理性能检验报告; Quality certificates of materials, parts and components at the factory exit, compatibility test reports of silicone structural adhesives and physical performance inspection reports of curtain walls; -03零碳面材复合板的物理性能试验报告; The physical performance test report of zero-carbon surface material composite panels; 04隐蔽工程验收文件; Acceptance documents of concealed works; 05施工安装自检记录; Self-inspection records of construction and installation; 06预制构件出厂质量合格证书; Quality certificates of prefabricated components at the factory exit; 07其他质量保证资料。 Other quality guarantee materials.
募墙工程观感检验应符合下列规定: Theinstallationof theMeisen zero-carbon surfacematerial compositepanel curtain wall should be carried out after the acceptance of the main project.
01幕墙外露框应横平竖直,造型应符合设计要求; The exposed frames of the curtain wall should be horizontal and vertical, and the shape should meet the design requirements;
-02幕墙的胶缝应横平竖直,表面应光滑无污染; The glue seams of the curtain wallshould be horizontal and vertical, and the surface should be smooth and free of pollution;
-03板材颜色应均匀,其色差可同色板相差一级;由于产品所模仿的天然 材料本身所具有的色差的差异不应视为色差; The colorof the plates should be uniform, and the color difference can be one level different from the color sample; The color diference of the natural materials that the product imitates should not be regarded as a color differencedue totheinherent differencesincolor.
04板材纹理应同样板相符,花纹图案应符合设计要求;由于产品所模仿 的天然材料本身所具有的纹理和花纹图案的差异不应视为纹理和花纹 图案不一致; The texture of the plates should be consistent with the sample, and the pattern should meet the design requirements; The differences in texture and pattern of the natural materials that the product imitates should not be regarded as inconsistent texture and pattern.
-05沉降缝、伸缩缝、防震缝的处理,应保持外观效果的一致性,并应符 合设计要求; The treatment of settlement joints, expansion joints and seismic joints should maintain the consistency of the appearance effect and meet the design requirements;
06板材表面应平整,站在距幕墙表面3m处肉眼观察时不应有可觉察的 变形、波纹或局部压砸等缺陷;产品本身纹理所固有的凹凸、波纹、 坑洞等不在异议范围内; The surface of the plates should be flat. when observing with the naked eye at a distance of 3m from the surface of the curtain wall,there should be no detectable deformations, ripples or local crushing and other defects; The inherent concavities,ripples,pits and holes in the texture of the product itself are not within the scope of objections; 07 板材表面不得有非天然材料属性而是人为损坏性的凹坑、缺角、裂 缝、斑痕。 The surface of the plates shallnot have pits, missing corners, cracks and stains that are artificially damaged rather than attributed to the nature of the material.
幕墙工程观感检验应符合下列规定:
The installation of the Meisen zero-carbon surface material composite panel curtain wall should be carried out after the acceptance of the main project.
一01渗漏检验应按每 100\mathsf{m}^{2} 幕墙面积抽查一处,并应在易发生漏雨的部位 如阴阳角等处进行淋水检查; Leakage inspection shouldbeconducted at one spotfor every 100\;\mathsf{m}^{2} of curtain wall area, and water spraying inspection should be carried out at theparts pronetorainleakage,such asinternal and external corners.
一02每平方米板材的表面质量应符合表4的规定。
The surface quality of each square meter of the plate should comply with the provisions in Table 4.
| 项 目 | 质量要求 |
| 0.1-0.3mm宽划伤痕 | 长度小于100mm不多于8条 |
| 擦伤 | 不大于500mm2 |
03每平方米板材的表面质量应符合表5的规定;
The surface quality of each square meter of the plate should comply with theprovisionsof Table5;
| 项 目 | 质量要求 |
| 0.1~0.3mm划伤 | 长度小于100mm不多于2条 |
| 擦伤 | 不大于500m2 |
04板材的安装质量应符合表6的规定;
The installation quality of the plates should comply with the provisions of Table6:
| 项 目 | 允许偏差(mm) | 检查方法 | |
| 竖缝及 墙面垂直缝 | 幕墙层高不大于3m | ≤2 | 激光经纬 仪或经纬 |
| 幕墙层高大于3m | ≤3 | ||
| 幕墙水平度(层高) | ≤2 | 仪 2m靠尺,钢板尺 | |
| 竖缝直线度(层高) | ≤2 | 2m靠尺、钢板尺 | |
| 横缝直线度(层高) | ≤2 | 2m常尺、钢板尺 | |
| 拼缝宽度(与设计值比) | ≤1 | 卡尺 | |
05幕墙的安装质量应符合表7的规定;
The installation quality of the curtain wall should comply with the provisionsof Table7;
| 项 目 | 允许偏差(mm) | 检查方法 | |
| 幕墙垂直度 | 幕墙高度不大于30m | 激光经纬 仪或经 纬仪 | |
| 幕墙高度大于30m,不大于60m | ≤15 | ||
| 幕墙高度大于60m,不大于90m | ≤20 | ||
| 幕墙高度大于90m | ≤25 | ||
| 竖向板材直线度 | 2m靠尺、寨尺 | ||
| 横向板材水平度不大于2000mm | ≤2 | 水平仪 | |
| 同高度相邻两根横向构件高度差 | ≤1 | 钢板尺、塞尺 | |
| 幕墙横向水平度 | 不大于3m的层高 | 水平仪 | |
| 大于3m的层高 | ≤5 | ||
| 分格框对角线差 | 对角线长不大于2000mm | ≤3 | 3m钢卷尺 |
| 对角线长大于2000mm | ≤3.5 | ||
)幕墙工程抽样检验数量应按现行行业标准《玻璃幕墙工程技术规范》(IG)102)的有关规定执行。
The quantity of sampling inspection for curtain wall projects should be implemented in accordance with the relevant provisions of the current industry standard "Technical Code for Glass Curtain Wall Engineering" (IG) 102).
07 保养与维修
Maintenance and repair)幕墙工程峻工验收后,应制定幕墙的保养、维修计划与制度,定期进行幕墙的保养与维修。
After the completion and acceptance of the curtain wall project, a maintenance and repairplan and system for the curtain wall should be formulated, and the curtain wall should be maintained and repaired regularly.
幕墙的保养应根据幕墙墙面积灰污染程度,确定清洗幕墙的次数与周期,每年至少应清洗一次。
The maintenance of the curtain wall should determine the frequency and cycle of cleaning thecurtain wall based onthe degree of dust and pollution on the curtain wall surface.It should be cleaned at least once a year.
幕墙在正常使用时,使用单位应每隔5年进行一次全面检查。应对板材、密封条、密封胶、硅酮结构密封胶等进行检查。
During the normal use of the curtain wall, the userunit should conduct a comprehensiveinspectioneveryfiveyears.Inspectionsshouldbecarried out onplates,sealing strips,sealants,siliconestructural sealants,etc.
对幕墙进行保养与维修中应符合下列安全规定:
The following safety regulations should be met during the maintenance and repairof thecurtainwall:
01不得在4级以上风力或大雨天气进行幕墙外侧检查、保养与维修作业; Inspections,maintenance andrepair operations on the outside of the curtain wall shall not be carried out in wind force above level4 or in heavy rainweather;
一02检查、清洗、保养维修幕墙时,所采用的机具设备必须操作方便、安全 可靠: When inspecting, cleaning, maintaining and repairing the curtain wall, the machinery and equipment adopted must be easy to operate,safe and reliable:
一03在幕墙的保养与维修作业中,凡属高处作业者必须遵守现行行业标准《建筑施工高处作业安全技术规范》(G)80)的有关规定。
In the maintenance and repair operations of the curtain wall, all those engaged in work at heights must comply with the relevant provisions of the current industry standard"Safety Technical SpecificationsforWork at Heights in Building Construction" (IG)80).
幕墙的检查与维修应按下列规定进行:
The inspection and repair of the curtain wall should be carried out in accordancewiththefollowingprovisions:
一01当发现螺栓松动,应及时拧紧,当发现连接件锈蚀应除锈补漆或更换; When it is found that the bolts are loose, they should be tightened in time. When it is found that the connecting parts are rusted, the rust should be removed,repainted orreplaced;
一02发现板材松动、破损时,应及时修补与更换; When it is found that the plates are loose or damaged, they should be repaired and replaced intime;
一03发现密封胶或密封条脱落或损坏时,应及时修补与更换; When it is found that the sealant or sealing strip falls off or is damaged, it should be repaired and replaced in time;
一04发现幕墙构件和连接件损坏,或连接件与主体结构的锚固松动或脱落 时,应及时更换或采取措施加固修复; When it isfound that the curtain wall components and connectors are damaged, or the anchoring of the connectors and the main structure is loose or falls off, they should be replaced in time or measures should be takenforreinforcement andrepair;
-05应定期检查幕墙排水系统,当发现堵塞时,应及时疏通; The curtain wall drainage system should be inspected regularly. When it is found to be clogged,it should be dredged in time;
-06当五金件有脱落、损坏或功能障碍时,应进行更换和修复; When the hardware falls off, is damaged or has functional disorders, it should bereplaced and repaired;
一07当遇到台风、地震、火灾等自然灾害时,灾后应对幕墙进行全面检查, 并视损坏程度进行维修加固。 When encountering natural disasters such as typhoons, earthquakes, and fires,a comprehensive inspection of the curtain wallshould be conducted after the disaster, and repairs and reinforcements should be carried out depending on the degree of damage.
美森(深圳)材料科技有限公司Meson (Shenzhen) Material Science Co.Ltd.
深圳市光明区光明街道碧眼社区华强创意公园5栋B座1201、1205 ⊚ 1201, 1205,Building B,No.5, Huaqiang Creative Park,Biyan Community,Guangming Street,GuangmingDistrict,Shenzhen,China
+86-0755-21061007 ⊚ work@mesoneco.com \circleddash www.mesoneco.com \circledast